The George Hotel


Hot Water Heat Pump

May 2015

PROBLEM

Due to its age, The George’s hot water supply system was due for replacement. DETA Consulting had identified in a previous energy audit that a hot water heat pump could be a more cost effective option to operate at site, however they needed to quantify the potential savings and how the heat pump would operate

SOLUTION

DETA Consulting identified the most feasible option for use at site, and prepared a business case for the George to approve. DETA Consulting then worked through a third party contractor to install the heatpump system, complete with gas backup for electrical load shedding.

OUTCOME

The heatpump reduces the George’s hot water generation cost by $35,000 – a 46% reduction in cost. In addition, the George now has a long term solution for their domestic hot water supply and no worries about extra maintenance for many years.